Fit-out

Interior fit-out in Japan: process and published time guides

A store interior in Japan usually moves from a hearing and site survey, through design and estimate, into construction and official inspections. The steps and time guides below are those already published on this site. Official filing windows from the health centre and the fire department are shown separately, so that a programme is not planned from the construction period alone.

Published 13 November 2026 · Shop Design Laboratory

A bar interior
A bar interior by Shop Design Laboratory.

Ten steps from inquiry to aftercare

You may contact us at any stage. When you commission both design and construction, design, basic planning, and perspective drawings are provided at no charge.

  1. Inquiry and hearing

    After you contact us by phone or form, we discuss your aims, schedule, and budget. In some cases we can provide a rough estimate from the form alone.

  2. Property viewing and site survey

    Viewings take about one hour. We measure the space, check equipment and remaining fixtures, and take photographs.

  3. Basic design

    A plan and design drawings typically take about one week to ten days.

  4. Estimate and colour scheme

    Estimates are usually ready within one week after the design. We obtain samples of finishes and materials for review.

  5. Regulatory checks and revisions

    We check applicable laws and ordinances and prepare applications. Drawings can be revised as many times as needed.

  6. Cost, schedule, and funding

    We propose cost reductions that do not compromise quality, and can share information on leasing and financing. Night work is available.

  7. Contract and detailed design

    The contract sets out the scope and warranties. Detailed design usually takes about two weeks. Construction insurance is arranged.

  8. Construction and official applications

    Work begins after we greet neighbouring premises. The assigned designer supervises the site. We file the required applications on your behalf.

  9. Handover and inspections

    We hand over the premises after final cleaning and a checklist review, and attend official inspections through approval. The operator (or a proxy) must also attend.

  10. Aftercare

    We handle even a single light bulb and keep records of consumables. Please contact us after opening, even with small matters.

Published time guides

The durations below are only those written on the current site. Steps without a published duration are marked as such. No additional numbers have been added.

01 Inquiry and hearing
Duration not stated
02 Property viewing
About 1 hour
03 Basic design
About 1 week to 10 days
04 Estimate and colour scheme
Within 1 week after the design
05 Regulatory checks
Duration not stated
06 Cost adjustment
Duration not stated
07 Detailed design
Usually about 2 weeks
08 Construction and applications
Varies by project (see table)
09 Handover and inspections
Duration not stated
10 Aftercare
After opening

The current site’s FAQ also notes a shortest published case: design in one week and construction in ten days for a 20-tsubo bar. That is an example, not a standard period.

Construction period by type of work

Figures as printed on this site’s gallery category pages. Prices are omitted here.

Type of workConstruction period (as published)Source page
Bar1–3 weeksRestaurants / bar gallery
Nightclub / cabaret3 weeks–60 daysRestaurants / bar gallery
Café, restaurant, or dining3 weeks–40 days (one published example: 4 weeks)Restaurants / bar gallery
Japanese cuisine, sushi, or yakiniku3 weeks–40 days (one published example: 30 days)Restaurants / bar gallery
Specialty stores2–3 weeksSpecialty store gallery
Apparel stores1–3 weeksSpecialty store gallery
OfficePublished examples: 3 weeks and 2 weeksOffice gallery
Hair salonPublished example: 4 weeksHair salon gallery
Clinic1–4 weeksClinic gallery
Esthetic and other beauty salons1–4 weeksSalon gallery
Dance studio or gallery2–3 weeksSalon gallery
A yakiniku restaurant interior
Yakiniku restaurant.
A dance studio
Dance studio.

Official windows that sit around the works

These are not extra construction days. They are filing and inspection points that must be built into the programme, especially for restaurants.

Before construction startsFor a food business, Tokyo ward health centres ask you to bring drawings and consult them before work begins, so that the layout can be checked against facility standards. See the restaurant permit guide.
7 days before work startsIn Tokyo, a construction-plan notification to the fire station is required at least seven days before repairs, remodelling, or partition changes begin.
About 10 days before completionThe Tokyo Metropolitan Government asks that restaurant-permit application documents be submitted to the health centre around ten days before the planned completion date. Special wards may use their own forms.
After completionThe health centre inspects the finished facility. A permit is issued only after the facility meets the standards; if it does not, items must be corrected and the inspection repeated. Allow time after approval for the permit document to be issued — Shinagawa City notes that this can take several days.
7 days before use startsIn Tokyo, a use-start notification must reach the fire station at least seven days before you start using the premises, even if little or no construction was done.
About 3 weeks before openingOur opening chart suggests ordering printed matter such as menus and shop cards about three weeks before opening. Website and printed-matter design are charged separately from the construction contract.
About 1–4 weeks before openingThe same chart notes a training and test-run period of about one to four weeks, to adjust circulation, air-conditioning, and lighting.

Sources

This guide is not legal advice. It is general information for planning a store in Japan, checked against official sources on 13 November 2026 (JST). Laws, ordinances, fees, and forms differ by municipality and can change. Please confirm the current rules with the competent authorities — for example the local health centre, fire station, building official, Legal Affairs Bureau, or Immigration Services Agency — and with qualified professionals.

Talk through your opening plan

Shop Design Laboratory (Design Directors Co., Ltd.) provides store design and construction as one project in Tokyo, Kanagawa, Saitama, and Chiba. When you commission both design and construction, design, basic planning, and perspective drawings are provided at no charge. Consultations and estimates are free. We can accompany a property viewing and file required official applications on your behalf.

Phone hours: weekdays 9:00–18:00 (Japan time). International: +81-3-6279-3077. You may use the contact form, call, or email us.

More in this guide

For those considering opening or renovating a store, Shop Design Laboratory is a one-stop partner for shop design and interior fit-out in Tokyo.

Consultations and estimates are free. A designer joins the first meeting.